PDQIE Service Vehicles   Industrial - Commercial  PDQ Industrial Electric  Electrical Contractor   Reddy Kilowatt

PDQ Electric Corp

NJ, PA, DE, MD, NY, CT, DC, MA, RI

 

HOME SERVICE AREA QUOTE REQUEST EMERGENCY 24-7 CONTACT PDQIE SITE MAP

 

PDQIE Panel Room

PDQIE - PDQ Industrial Electric

Critical Path (CPM) and Fast Track Projects


Critical Path (CPM) Scheduled Projects

The Critical Path Method, abbreviated CPM, or critical path analysis, is a mathematically based algorithm for scheduling a set of project activities. It is an important tool for effective project management.

It was developed in the 1950s in a joint venture between DuPont Corporation and Remington Rand Corporation for managing plant maintenance projects. Today, it is commonly used with all forms of projects, including construction, software development, research projects, product development, engineering, and plant maintenance, among others. Any project with interdependent activities can apply this method of scheduling.

The essential technique for using CPM is to construct a model of the project that includes the following:

A list of all activities required to complete the project (also known as Work breakdown structure), The time (duration) that each activity will take to completion, and The dependencies between the activities.

Using these values, CPM calculates the longest path of planned activities to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer). In project management, a critical path is the sequence of project network activities which add up to the longest overall duration. This determines the shortest time possible to complete the project. Any delay of an activity on the critical path directly impacts the planned project completion date (i.e. there is no float on the critical path). A project can have several, parallel, near critical paths. An additional parallel path through the network with the total durations shorter than the critical path is called a sub-critical or non-critical path.

These results allow managers to prioritize activities for the effective management of project completion, and to shorten the planned critical path of a project by pruning critical path activities, by "fast tracking" (i.e., performing more activities in parallel), and/or by "crashing the critical path" (i.e., shortening the durations of critical path activities by adding resources).

Originally, the critical path method considered only logical dependencies between terminal elements. Since then, it has been expanded to allow for the inclusion of resources related to each activity, through processes called "activity-based resource assignments" and "resource leveling". A resource-leveled schedule may include delays due to resource bottlenecks (i.e., unavailability of a resource at the required time), and may cause a previously shorter path to become the longest or "resource critical" path. A related concept is called the critical chain, which attempts to protect activity and project durations from unforeseen delays due to resource constraints.

Since project schedules change on a regular basis, CPM allows continuous monitoring of the schedule, allows the project manager to track the critical activities, and alerts the project manager to the possibility that non-critical activities may be delayed beyond their total float, thus creating a new critical path and delaying project completion. In addition, the method can easily incorporate the concepts of stochastic predictions, using the Program Evaluation and Review Technique (PERT) and event chain methodology.

Currently, there are several software solutions available in industry that use the CPM method of scheduling, see list of project management software. However, the method was developed and used without the aid of computers.

A schedule generated using critical path techniques often is not realized precisely, as estimations are used to calculate times: if one mistake is made, the results of the analysis may change. This could cause an upset in the implementation of a project if the estimates are blindly believed, and if changes are not addressed promptly. However, the structure of critical path analysis is such that the variance from the original schedule caused by any change can be measured, and its impact either ameliorated or adjusted for. Indeed, an important element of project postmortem analysis is the As Built Critical Path (ABCP), which analyzes the specific causes and impacts of changes between the planned schedule and eventual schedule as actually implemented.

Fast-Track Projects

Another way to shorten your schedule is through Fast-Tracking. Fast-Tracking is the process of rescheduling tasks to be performed in parallel that were originally planned in series. Like Project Schedule Crashing, Fast-Track works on tasks in the Critical ath. If you reschedule two tasks originally in series to be done in parallel, you are in effect cutting the time to do the task to half. And like Project Schedule Crashing, Fast-Track may bring complications to the feasibility of the Project Schedule. For one, do not Fast-Track tasks that are strictly interdependent of one another, such as applying a second coat of paint. In doing a paint job, you cannot schedule second coating and first coating in parallel, it's just not possible. Fortunately, there are tasks that can be made parallel, such as building a wall and inatalling floor covering or a ceiling; while these tasks may cause complications, these are achievable when done right.

In fine-tuning your Project Schedule, you can be creative, but be certain that you have calculated the net benefit.

Call PDQIE to Discuss Your Project Schedule (877) PDQ-4-FIX